PROJECTS

A selection of signature projects.

DJI_20241228024051_0188_D-1123-1 Projects

OCEAN RESCUE HEADQUARTERS

IMG-20250103-WA0029 Projects

HISTORIC BRIDGES REHABILITATION AND PAINTING

North-Miami-Housing-Development-07j Projects

MIA North Terminal Public Restrooms Modernization

Leigh-Acres-07 Projects

LEHIGH ACRES DEVELOPMENT

02_Port-of-Miami-0001 Projects

PORT OF MIAMI

03_library-06 Projects

CORAL GABLES LIBRARY

North-Miami-Housing-Development-07 Projects

NORTH MIAMI HOUSING DEVELOPMENT

FortLauderdaleAirport_T5_0001 Projects

FORT LAUDERDALE AIRPORT | TERMINAL 5

Sunset-and-Veterans-Parks-05 Projects

SUNSET AND VETERANS PARKS RENOVATION

Lehigh Acres Development

Project Overview

• Project Location: Various locations in Lehigh Acres, FL.
• Construction Dates: Started May 2022 (ongoing project)
• Self-Performed Scope: 100% of the project.

Scope of work​

The project entails creating an 80-unit housing community in Lehigh Acres,
encompassing diverse elements such as:

• New construction
• Civil and site improvements
• Roadway and paving
• Drainage systems
• Utilities installation (sewer and water)
• Structural infrastructure
• Landscape design
• MEP (mechanical, electrical, plumbing) installations
• Rigorous QC/QA (quality control/quality assurance) protocols.

Future phases of the project will expand the community with additional houses and individual lots, covering a total land area exceeding 25 acres.

Managing this project presented formidable challenges due to the extensive material requirements. Coordinating procurement, delivery, and handling necessitated meticulous planning for seamless progress and timely completion.

In summary, the integration of a concrete slab foundation, reinforced concrete structure with CMU blocks, and wooden trusses establishes a robust and reliable framework for the residences, guaranteeing longevity and enduring structural stability for the foreseeable future.

CORAL GABLES LIBRARY

Project Overview

  • Project Location: Coral Gables, Miami, FL.
  • Construction Dates: May 2021 to April 2023
  • Contract Amount: $4,370,308.48
  • Self-Performed Scope: 100% of the project.

Scope of work

The project involved renovating a 28,446 square foot historical building, the project included but was not limited to:

  • Complete interior and roof demolition and disposal.
  • Asbestos abatement
  • MEP and Interior full renovation.
  • Installation of impact-resistant windows and doors.
  • Installation of new ceilings, carpeting, tiling, painting, other.
  • New kitchen and restrooms.
  • New special millwork.
  • Installation of new special lighting fixtures and translucents
  • Restoration of historical elements including furniture, floors, and stone walls
  • New roof installation.

Unique challenges arose in preserving historical artifacts like furniture and sculptures, demanding careful attention throughout the renovation process.

 Despite these complexities, the project successfully honored the building’s legacy, achieving its renovation objectives while respecting its historical significance.

FORT Lauderdale Airport - Terminal 5

Project Overview

• Project Location: Fort Lauderdale – Hollywood Int. Airport, Fort Lauderdale, FL.
• Construction Dates: Started November 2023 (ongoing project)
• Self-Performed Scope: 100% of the project.

Scope of work

The project involved design-built electrical and plumbing connections for connex trailers and related activities. This included but was not limited to:
• Design-built and permit process
• Earthworks
• Utilities installation
• Sewer and plumbing connections
• New tanks installation
• Electrical connections
• New electrical panels
• Fiber optic scope
• Asphalt restoration
The project faces challenges due to its complexity, especially regarding security and working within an airport environment, as well as dealing with existing underground utilities.
However, the commitment is to deliver high-quality work while ensuring strict adherence to safety and regulatory standards.

North Miami Housing Development

Project Overview

• Project Location: North Miami and Hallandale Beach, FL.
• Construction Dates: Started April 2023 (ongoing project)
• Self-Performed Scope: 100% of the project.

Scope of work

The initial phase comprises three houses. The scope of work encompasses a
comprehensive range of tasks, including but not limited to:
• Design and Permitting
• Site Preparation and Earthworks
• Foundation Construction and Building Erection
• Concrete Structure Installation and Masonry Work
• Roofing and Installation of Openings
• Electrical, Plumbing, and Mechanical Installations
• Meticulous Finishing Touches and Custom Millwork
• Private Pool Construction and Landscaping
• Irrigation System Setup and Furnishing
Our unwavering commitment to delivering exceptional quality and attention to detail in every facet of this project ensures the creation of beautiful homes that harmonize with the essence of these communities and and add value to the neighborhood.

Sunset and Veterans Parks renovation

Project Overview

• Project Location: Tamarac, FL.
• Construction Dates: October 2021 to December 2023
• Contract Amount: $1,897,703.97
• Self-Performed Scope: 100% of the project.

Scope of work

The project aimed to revitalize and enhance two parks in Tamarac: Sunset Point and Veterans Park. Key aspects of the project included:
• Construction of new asphalt parking lots with specialized markings
• Building new structures using concrete, CMU blocks, and roofing materials
• MEP installation for interior and exterior needs
• Sidewalk and paving installation
• Landscaping enhancements
• Underground utility work
• Creation of a circular colored concrete slab for a veterans’ monument Effective coordination among various trades was essential throughout the project. Tasks ranged from demolishing old structures to constructing new buildings, landscaping, and drainage installations. The addition of sidewalks, colored concrete slabs, and fences not only improved functionality but also enhanced aesthetics. Notably challenging was the design and construction of a monument dedicated to honoring veterans, requiring careful attention to unique design requirements.

Port of Miami

Project Overview

• Project Location: Port of Miami Cruise Terminal, Miami, FL.
• Construction Dates: January 2018 to September 2019
• Contract Amount: $2,218,742.00
• Self-Performed Scope: 100% of the project.

Scope of work

The project involved the installation of a new Video Wall and LAN Room Relocation, encompassing a wide range of activities, including but not limited to:
• Selective demolition and disposal of ceilings, partitions, and HVAC ducts
• Installation of new HVAC ducts, doors, frames, glass partitions
• Lighting installation
• Card readers installation
• Electrical connections setup
• IT conduits installation
• Fire alarm and low voltage systems setup
• Fiber optics conduits installation
• Security film installation for windows
• Server racks setup
• Gypsum repairs
• Carpeting and floor tiles installation, ACT ceiling Installation, Painting.
It’s worth noting that this terminal was fully operational, serving passengers boarding cruises.
Given the specialized location and stringent security measures in place, the logistics of this project were particularly crucial. Our team adeptly navigated these challenges, ensuring meticulous coordination of materials, personnel, and equipment.

OCEAN RESCUE HEADQUARTERS

Project Overview

Location: Crandon Park, 7200 Crandon Boulevard, Key Biscayne, Florida.
Construction Dates: Ongoing project.
Self-Performed Scope: 100% of the project.

Scope of work​

The project involves the construction of the new Ocean Rescue Headquarters at Crandon Park, a single-story CBS structure spanning approximately 7,954 SF. The facility is designed to meet the operational needs of Miami-Dade Fire Rescue life safety and Ocean Rescue support staff while adhering to sustainable construction standards and achieving LEED Silver Certification.

Key Features:

  • Educational Lobby
  • Officer Offices
  • Safety Support Dispatch
  • Training Room
  • Lounge and Exercise Rooms
  • Men’s and Women’s Locker Rooms
  • Vehicles and Equipment Garage
  • Public Bathrooms for beach visitors

The construction scope includes site clearing, civil and structural work, utilities installation, interior build-out, exterior finishes, landscaping, and advanced building systems such as fire protection, emergency power, and security systems. All work aligns with the Miami-Dade PROS Master Plan Guidelines to ensure functionality, sustainability, and integration with the surrounding environment.

HISTORIC BRIDGES REHABILITATION AND PAINTING

Project Overview

Location: Curtiss Parkway over Miami and South Hook Canal, Miami Springs, FL, 33166.
Project Title: Historic Bridge No. 874129 and 874130 Rehabilitation and Painting.
Construction Dates: Ongoing project.
• Self-Performed Scope: 100% of the project.

Scope of work

This project focuses on the rehabilitation and preservation of two historic bridges, Bridge Nos. 874129 and 874130, located along Curtiss Parkway over Miami Canal. The work encompasses all necessary operations to restore and enhance the structural integrity, functionality, and aesthetic appeal of these historic structures.

Key Tasks:

  • Concrete Repairs
  • Structural Steel Repairs
  • Structural Steel Painting
  • Lighting Upgrades
  • Signage Updates
  • Aesthetic Improvements
This project aims to honor the historical significance of the Curtiss Parkway bridges while ensuring they meet modern structural and safety standards for years to come.

MIA North Terminal Public Restrooms Modernization

Project Overview

Project Name: MIA North Terminal Public Restrooms Modernization Group 1
Location: Miami International Airport, North Terminal, Miami, FL
Construction Dates: Ongoing project
Self-Performed Scope: 100% of the project

Scope of work

This project involves the comprehensive interior renovation, modernization, and ADA compliance upgrades for four sets of public restrooms (male, female, unisex, and janitor’s closet) located in Terminal D of Miami International Airport.

Key Tasks:

  • Interior Renovation
  • Toilet Accessories Installation
  • Plumbing Systems Upgrade
  • Power and Lighting Modernization
  • Fire and HVAC Systems Modifications
The demolition and renovation activities will be executed in a minimum of two phases to minimize disruptions to airport operations. This project aims to deliver modernized, accessible, and aesthetically pleasing restroom facilities that meet the highest standards of safety, functionality, and ADA compliance, enhancing the overall passenger experience at Miami International Airport.

WHAT WE OFFER


HE Builders offers a complete range of construction services including but not limited to general contracting, plumbing contracting, mechanical contracting, unlimited electrical contracting, fire protection contracting focused in commercial and government contracting.

HE Builders services capabilities include pre-construction, construction and post-construction services.

HF4_Probar-portada_800x449 Projects
Get an estimate for your project

You can leave us a message here or you can come visit us around the corner and meet the team. Let us inspire you!